Answer:
Check the explanation
Step-by-step explanation:
Activity Type Total Overhead Cost Activity Activity Rate ( Overhead Cost /Activity)
Handling Materials 6,25,000 1,00,000 6.25 per part
Inspecting Products 9,00,000 1,500 600.00 per batch
Processing Pur Order 1,05,000 700 150.00 per order
Paying Supplies 1,75,000 500 350.00 per invoice
Insuring 3,00,000 40,000 7.50 per Sqr Feet
Designing Packaging 75,000 2 37,500.00 perPack