Answer:
the process capability index is 0.002 and Since the capability index is < 1, therefore the process is not capable of producing the desired result.
Step-by-step explanation:
Formula to calculate process capability index is given below-
…… (1)
Here
Mean () = 1.002
Lower specification limit (LSL) =
Upper specification limit (USL) =
Standard deviation () = 1.002 inch