Answer:
Fully work unit = 13,000units
Step-by-step explanation:
We are given
New units introduced = 15,600
Closing work in progress = 2,300
Fully work unit is the number of units started and completed during the period.
Now, to evaluate the fully work units, we use the following method
Fully work units = New units introduced - closing work-in progress
Fully work units = 15,600 - 2,300 = Fully work units = 13,300 units
From the above calculation, we can say units started and was completed during the period of 13,300 units