Consider the steps in a bicycle-factory assembly line: Step 1: rate = 120 handlebars per hour Step 2: rate = 60 sets of wheels per hour Step 3: rate = 240 seats per hour What is the fastest rate at which the assembly line can produce complete bicycles?

User Xpepermint
by
4.8k points

2 Answers

5 votes

Answer:60 and slowest determines overall

Step-by-step explanation:

I took the warm up assignment

User Doug Finke
by
5.0k points
3 votes

Answer:

60 bicycles

Step-by-step explanation:

The slowest step determines the overall rate of the process.