Answer:
B) The production department had to use more materials since the quality of the materials was inferior.
1,000 more pounds of materials were used than budgeted, and that can only mean that the workers didn't do their job properly and wasted materials, or the new materials purchased at a lower cost were not the same quality as previously purchased materials.
Step-by-step explanation:
The other options are wrong because:
- A. The overall materials variance is positive, no further analysis is necessary. = FALSE, YOU DO NOT USE LESS MATERIALS FOR PRODUCING SOMETHING, OR IF YOU DO, THEN YOU DID SOMETHING WRONG.
- C. The purchasing manager paid more than expected for materials. = FALSE, THE PRICE OF MATERIALS ACTUALLY WAS LOWER = $97,000 / 25,000 LBS. = $3.88 PER LB. WHICH IS CHEAPER THAN $4
- D. Production workers were more efficient than anticipated. = FALSE, EFFICIENCY CAN DECREASE PRODUCTION TIME, MACHINE USE OR TOTAL OUTPUT, BUT IT DOESN'T EXPLAIN LESS MATERIALS USED.