To effectively track the Sprint progress, Scrum mandates A. Preparing Sprint burn down charts B. Increasing the transparency by frequently updating the remaining work C. Earned Value approach

User Rkallensee
by
4.2k points

2 Answers

1 vote

Final answer:

Scrum mandates A. preparing Sprint burn down charts and increasing transparency by frequently updating the remaining work to effectively track Sprint progress.

Step-by-step explanation:

In Scrum, to effectively track the Sprint progress, there are several practices that are mandated. One of these is preparing Sprint burn down charts. These charts show the progress of work throughout the Sprint, allowing the team to visualize how much work is remaining and how much has been completed.

Another practice is increasing transparency by frequently updating the remaining work. This can be done by using tools like Scrum boards or task management software to track the status of individual tasks. Finally, Scrum does not mandate the use of the Earned Value approach, as this approach is more commonly used in traditional project management methodologies.

User Joe Pineda
by
4.8k points
2 votes

Answer:

The answer is option A To effectively track the Sprint progress, Scrum mandates Preparing Sprint burn down charts

Step-by-step explanation:

Sprints are time-boxed periods of one week to one month, during which a product owner, scrum master, and scrum team work to complete a specific product addition. During a sprint, work is done to create new features based on the user stories and backlog. A new sprint starts immediately after the current sprint ends.

Some scrum teams deploy new product features for use at the end of each sprint. For scrum teams with a release with every sprint, the time to market is simply the sprint length, measured in days.

A sprint burn down chart shows the progress the development team is making and is a powerful tool for visualizing progress and the work remaining.