Answer:
$528,000
Step-by-step explanation:
Total cost of direct materials purchases:
April = $400,000
May = $480,000
June = $560,000
Cash payments are 60% in the month of purchase and 40% in the following month.
Budgeted cash payments for June:
= 60% of direct materials purchases in June + 40% of direct materials purchases in May
= (0.6 × $560,000) + (0.4 × $480,000)
= $336,000 + $192,000
= $528,000