Work Breakdown Structures typically include one or more intermediate levels. Which of the following statements correctly describe the nature of these intermediate levels? ​ a. They generally represent the resource assignments to create the final deliverables. b. They generally represent the sequence and timing of work packages c. They generally represent items that need to be created in order to produce the final deliverables. d. They generally represent the raw materials required to create the final deliverables.

1 Answer

4 votes

Answer:

c. They generally represent items that need to be created in order to produce the final deliverables.

Step-by-step explanation:

Work Breakdown Structure (WBS) is a tool that the project manager uses to progressively divide deliverables into smaller pieces. It gives framework that can be used as a basis for further planning activities. They are displayed in an indented outline format.