Answer:
$142,524
Step-by-step explanation:
The computation of the total cost assigned to the ending work in process
inventory is shown below:
As we know that
Total cost = Material + Labor
where,
Material = 21,400 units × 100% × $3.60 = $77,040
And,
Labor = 21,400 units × 60% × $5.10 = 65,484
So, the total cost is $142,524
We simply added material and the labor cost according to their completion percentage and its cost per equivalent units