Last year, Product H50E involved 9 customer orders, 666 assembly hours, and 77 batches. How much overhead cost would be assigned to Product H50E using the activity-based costing system

User Serj Sagan
by
4.3k points

1 Answer

3 votes

Answer:

$5778.31

Step-by-step explanation:

The correct answer is as follows:

Overhead cost = 9*31.62+666*2.86+77*46.61

= 5778.31