Complete Question
The complete question is shown on the first uploaded image
Answer:
The number of CNC machine required is

Step-by-step explanation:
From the question awe are told the
The machine availability is
85%
The Rejection time is
4%
The lapping time is
20 minutes
The time to work between machines is


The loading and unloading time

For one the loading and unloading time would be
Substituting values


for the 8 different sizes of the block the loading and unloading time would be

From the the target is given as

The available time is given as



The quantity of sets of block to be lapped by one machine per week would be

%

sets
Hence
The number of CNC lapping machine would be

