Answer:
b. 2.5 weeks
Step-by-step explanation:
Data provided
Own ships = 10
Serve = 2,000 passengers each week
Each cruise Ship carry = 500 passengers
So, here Inventory is passengers
Inventory on voyage = Own ships × Number of passenger per cruise ship
10 × 500
= 5,000 passenger
Passenger serving rate = 2000 passenger per week
Flow time = Inventory on voyage ÷ passengers serving rate
= $5,000 ÷ $2000
= 2.5 weeks