Answer:
2 hours
Explanation:
Given that the slow crew does the job in x/8 hours and fast in x/6
Equation:
x/6 + x/8 = 1 <------------1 because there is one job to be done
8x + 6x = 48
24x = 48
x = 2
It will take both groups working together 2 hours