Answer: $296,640
Step-by-step explanation:
Total Cost assigned to inventory
Calculation
The Materials cost $4 per unit * 30,900 units = $123,600
Conversion cost = $8 * per unit * 30,900 units =$247,200
Completion Rate
$247,200* 70 /100=$173,040
Total Costs
= $123,600 + $173,040 =$296,640