Answer:
The Total cost for potential job is $36,800.
Step-by-step explanation:
The potential cost is calculated as follows:
Direct Material $6,000
Direct Labour $16,000
Total Prime Costs $22,000
Overheads Cost:
(W-1) Maintenance: $12,800
(W-2) Inspection: $2,000
Total Job cost $36,800
Workings:
(W-1) Maintenance Overhead Rate is based on number of machine hours:
Formula: Total Maintenance cost/Total machine Hours
$800,000/25,000 = $32 per machine hours.
So the Maintenance cost for project is: 400 Machine hours × $32 = $ 12,800.
(W-2) Inspection Overhead Rate is based on inspection hours:
Formula: Total Inspection Cost/Total Inspection Hours
$400,000/800 = $500 per inspection hour
So the inspection cost for project is: 4 inspection hours × $500= $2,000