86.4k views
3 votes
(Tierman Gallery Part A) The Tierman Gallery distributes to its visitors a brochure to its collections. There are about 20800 visitors per year. The unit cost is $2, the holding cost for a brochure is 10% of the unit cost and it costs $30 to place an order. The unit time is 1 week and it takes 2 weeks till printed brochures are delivered. [OQ] (Tierman Gallery Part A) Tierman should place an order when the on-hand inventory reaches ___.

User Kfriend
by
4.8k points

1 Answer

3 votes

Answer:

TIERMAN SHOULD PLACE AN ORDER WHEN THE ON HAND INVENTORY REACHES: C. 800

Step-by-step explanation:

Annual demand (i.e. Number of visitors) = D = 20800

Ordering cost = F = $30

Unit holding cost = C = 10% of $2 /unit = $0.2 / unit

Weekly demand of visitors = Annual demand of visitors/ 52 weeks = 20800/ 52 = 400

Lead time for delivery of brochure = L = 2 weeks

Therefore, Reorder point = Weekly demand x Lead time (weeks) = 400 x 2 = 800

User Tonisha
by
4.5k points