Suppose that the requirements​ (in gallons) for the next four quarters are revised to 140 comma 000​, 60 comma 000​, 90 comma 000​, and 90 comma 000 respectively. If total demand is the​ same, what level of production rate is needed​ now, using the same strategy as​ above? The new quarterly production rate is nothing gallons. ​(Enter your response as an​ integer.)

1 Answer

3 votes

Solution and Explanation:

As per the given data:

Quarter 1 = 90000, Quarter 2 = 90000, Quarter 3 = 60000, Quarter 4 = 140000

a. Quarterly production rate is calculated as follows:

Q = ( 90000 + 90000 + 60000 + 140000 ) divide by 4

after calcualting the above equation, we get, = 95000 gallons per quarter tin order to meet the demand.

b. Anticipation inventory:

1 st quarter = 95000 minus 90000 = 5000 gallons

2 nd quarter = 95000 minus 90000 = 5000 + 5000 in prior quarter = 10000 gallons

3 rd quarter = 95000 minus 60000 = 35000 + 10000 in prior quarters = 45000 gallons

4th quarter = 140000 minus 450000 minus 95000 = 0 gallons.

User Michael Andersen
by
8.3k points

No related questions found

Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.

9.4m questions

12.2m answers

Categories