Answer:
$6 unfavorable
Step-by-step explanation:
The computation of the cost variance is shown below:
Cost variance = Standard cost - actual cost
where
Standard cost is
= $20 + 0.20 ×$26 + $40 × 0.20
= $20 + $5.2 + $8
= $33.2
And, the actual cost is $39.20
So the cost variance is
= $33.2 - $39.20
= $6 unfavorable
Since the actual cost is more than the actual cost which reflects the unfavorable variance