John Williams, manager of Phoenix Entertainment, wants to compute the variable overhead efficiency variance for the year. He has the following details: Variable overhead flexible budget variance (unfavorable) $23,625 Budgeted input quantity allowed for actual output 9,000 units Actual input quantity used of cost-allocation base used 10,125 units Budgeted variable overhead cost per unit of cost- allocation base $30 Actual variable overhead cost per unit of cost- allocation base $29 What will be the variable overhead efficiency variance for the year

1 Answer

1 vote

Answer:

2nd option is correct.

Step-by-step explanation:

Variable over head = (Actual Qty. - Standard Qty. ) * Standard cost

Efficiency variance

= (10125-9000) * 30

= $ 33750 (Un-Favorable)

2nd option is correct.

Variance is unfavorable because actual quantity used to produce is more than budgeted quantity allowed at that level of production.

User Mus
by
7.7k points
Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.