Answer:
Estimated manufacturing overhead rate= $110 per machine hour
Step-by-step explanation:
Giving the following information:
Estimated manufacturing overhead costs= $550,000.
Aaron allocates overhead costs based on machine hours.
The estimated total machine hours= 5,000 hours
To calculate the estimated manufacturing overhead rate we need to use the following formula:
Estimated manufacturing overhead rate= total estimated overhead costs for the period/ total amount of allocation base
Estimated manufacturing overhead rate= 550,000/5,000= $110 per machine hour