Once the project is chosen, planning the project begins. Various schedules will be created at different times in the project. For example, a conceptual schedule is created as the scope of work is being developed. When the project team includes major events and dates such as the starting date and the completion date, the team is said to have created a ________ schedule.

User Bkdraper
by
7.0k points

2 Answers

4 votes

Answer:

The correct answer is letter "C": Master.

Step-by-step explanation:

A Master Schedule includes all the steps in detail of a project including their expected beginning and ending date. A master schedule is a useful tool that allows managers to check on the progress of the work, moreover if all the objectives are being accomplished as planned. This type of schedule is fed by the Master Project Plan where the main and secondary objectives of a company are established.

User Andrei Koch
by
6.9k points
2 votes

Answer:

The team is said to have created a Master Schedule

User Tin Nguyen
by
7.4k points