Suppose the total number of minutes provided exceeds the total number of minutes estimated and that the total dollar cost of the minutes provided exceeds the budgeted cost of estimated minutes. This outcome is most likely to be a function of:

A. technicians being less competent than anticipated at their level
B. technicians being more competent than anticipated at their level
C. in at least one of the higher technical levels, more minutes being provided than budgeted
D. in at least one of the higher technical levels, fewer minutes being provided than budgeted

User Ben Lu
by
4.7k points

1 Answer

5 votes

Answer:

C) In at least one of the higher technical levels ,more minutes being provided than budgeted.

Step-by-step explanation:

For such discrepancy to exist ,it means the minutes dictates the effect of the dollar.