Answer:
True
Explanation
Resource leveling, or smoothing, is a method for developing a schedule that attempts to minimize the how requirements for resources are manged when the project completion time is fixed.Resource-limited scheduling is a method created for the sole purpose of coming up with a plan to create the shortest schedule; when the quantity of available resources is fixed and also when there might be an extension of the project completion time in order to keep within the resource limits.