a. only product A is produced = 1,824 units
b. only product B is produced = 3,120 units
c. A and B are produced in a mix of 25% A and 75% B = 444 units of A, and 2,220 units of B
Step-by-step explanation:
a. Only Product A is Produced
Number of hours of production per week = 40 hours
Converts this time to seconds we have
= 40 x 60 x 60 = 144,000 seconds
Setup time for Product A = 2 hours
Convert to seconds we get:
2 x 60 x 60 = 7,200 seconds
Product A is done in batches of 1000 units
Run time for Product A = 75 seconds (Time to produce a unit of Product A)
Hence time taken to produce 1000 units = 75 second x 1000 = 75,000 seconds
Hence Remaining time after producing 1000 units will be:
144,000 - (75,000 + 7,200) = 61,800 seconds
Hence the number of units that can be produced in this time, knowing that 1 unit takes 75 seconds to be produced = 61,800/75 = 824 units
Hence Total unit of Product A = 1000 + 824 = 1,824 units
b. Only product B is produced
Number of hours of production per week = 40 hours
Converts this time to seconds we have
= 40 x 60 x 60 = 144,000 seconds
Setup time for Product B = 1 hours
Convert to seconds we get:
1 x 60 x 60 = 3,600 seconds
Product B is done in batches of 500 units
Run time for Product B = 45 seconds (Time to produce a unit of Product A)
Hence time taken to produce 500 units = 45 second x 500 = 22,500 seconds
Hence Remaining time after producing 500 units of Product B will be:
144,000 - (22,500 + 3,600) = 117,900 seconds
Hence the number of units that can be produced in this time, knowing that 1 unit takes 45 seconds to be produced = 117,900/45 = 2,620 units
Hence Total unit of Product B = 500 + 2,620 = 3,120 units
c. A and B are produced in a mix of 25% A and 75% B
Setup time for Product A = 2 hrs
Set up time for Product B = 1 hr
Total setup time = 3 hours
Number of hours of production = 40 hours
Number of hours of production barring loss time = 40 hours - 3 hours = 37 hours
25% of Product A will use 25% of time, which is:
0.25 x 37 = 9.25 hours = 9.25 x 60 x 60 = 33,300 seconds
75% of Product B will use 75% of the useful time, which is:
0.75 x 37 = 27.75 hours = 27.75 x 60 x 60 = 99,900 seconds
Product A run time is 75 seconds, Hence total product in the time allocated:
= 33,300/75 = 444 units of Product A
Product A run time is 45 seconds, Hence total product in the time allocated:
= 99,900/45 = 2,220 units