Answer:
$302,100
Step-by-step explanation:
The Total Cost (TC) refers to the actual aggregate cost of producing a given quantity of output. Generally, total cost is the addition of variable cost and fixed cost of production.
In this question, we are given neither the total variable cost nor the fixed cost.
However, we are given the average cost (AC) which is unit cost of production that is be calculated as follows:
AC = TC/Q ……………………………………… (1)
Where,
AC = Average cost = $57
TC = Total cost = ?
Q = Output level of anchors = 5,300
Substituting the values above into equation (1) and solve for TC, we have:
$57 = TC/5,300
TC = $57 × 5,300 = $302,100
Therefore, the total cost of producing 5300 anchors is $302,100.