Answer:
NPV =$ 60,311.80
Step-by-step explanation:
The net present value (NPV) of a project is the present value of cash inflow less the present value of cash outflow of the project.
NPV = PV of cash inflow - PV of cash outflow
We can set out the cash flows of the project using the table below:
0 1 2 3
Operating cash flow 136,000 136,000 136,000
Initial cost (274,000)
Working capital (61,000 ) 61,000
Salvage value 15000
Net cashflow (335,000) 136,000 136,000 212,000.
PV inflow= (136000)× (1.1)^(-1) + (136,000× (1.1)^(-2) + (112,000)× (1.1)^(-3)
= 395,311.80
NPV =395,311.80 -335,000
=$ 60,311.80