The BEST approach to network representation of a large and hugely complex project is to: Use AOA. Represent all activities and relationships. Use AON. Simplify network logic and reduce it to the most meaningful relationships.

1 Answer

2 votes

Answer:

Simplify network logic and reduce it to the most meaningful relationships

Step-by-step explanation:

The above refers to a Logic Network which describes the sequencial activities in a project over a period of time. Here we are able to see which activity logically precedes/comes before or follows the other. The network logic can be used to identify the targets/achievements or the milestones reached in a project. It aids understanding of project workflow, timescale and relationships/dependencies.