Answer:
$160.00 per machine hour
Step-by-step explanation:
The plant-wide (blanket ) overhead absorption rate is calculated as follows:
Plant-wide OAR=
Total overheads of all the production departments/ Total machine hours
Plant-wide OAR = $(320,000 + 400,000)/(2,000+2,500) machine hours
=$160.00 per machine hour