You have just been assigned to oversee a series of projects. Functional areas will loan you personnel for each project and separate project managers will be responsible for separate projects. These project managers will report to you. Which project management structure is being used?

A. Pure Project
B. Task force
C. Matrix Project
D. Functional Project
E. PERT

User Mwhuss
by
5.0k points

1 Answer

4 votes

Answer:

C) Matrix Project

Step-by-step explanation:

A matrix project structure combines project teams with a functional structure, in other words, the projects' coordinator oversees the activities of several projects and each project leader manages a functional team. Matrix structures can be fairly complicated since lines of reporting and command overlap, but at the same time this type of organization is much more flexible.