Using PERT, Adam Munson was able to determine that the expected project completion time for the construction of a pleasure yacht is 15 months, and the project variance is 4, the probability that the project will be completed in 16 months is _ (Round to one decimal place)

2 Answers

0 votes

Answer:

approximately 0.7

Step-by-step explanation:

Pert Analysis is used to compute/sum up the various variances of a project along its critical path

using PERT

The mean value of project ( estimated project time ) = 15

project variance б = 4

standard deviation =
\sqrt{} б = 2

probability that project will be completed on or before 16 months

= P ( X ≤ 16 )

this means Z ≤
(X - 15)/(2) where X = 16

= Z ≤ 1

using the the normal distribution appendix for the Z value the probability of completing the project in 16 months would approximately be 0.7

User Vaebhav
by
4.4k points
4 votes

Answer:

The probability that the project will finish in 16 months is 0.7.

Step-by-step explanation:

From the data the mean time is given as
\mu=15

The variance is given as
\sigma^2=4\\

So the standard deviation is
\sigma=2\\

Now the X is given as 16 so

Calculating the z score as


z=(x-\mu)/(\sigma)\\z=(16-15)/(2)\\z=(1)/(2)=0.5

So for the z score of 0.5 the probability is given in Excel as

=NORMSDIST(0.5)

=0.69 ≈0.7

So the probability that the project will finish in 16 months is 0.7.