198k views
5 votes
hich of the following is not true regarding the use of simulation in multinational capital budgeting? a. It can be used to generate a probability distribution of NPVs. b. It can only be used for one variable at a time. c. It generates a probability distribution of NPVs by randomly drawing values for the input variable(s). d. It can be used to develop probability distributions of all variables with uncertain future values.

User Serhio
by
5.0k points

1 Answer

6 votes

Answer:

B. It can only be used for one variable at a time

Explanation:

Simulation can accommodate multiple variables at a time. The variables could be constraints such as time, amount, quantity, duration. A range of expected values must either be developed or provided for the variables before simulation models can then be applied to these ranges to generate a distribution of NPVs.

User Alecu
by
4.7k points