227k views
5 votes
Which of the following measures the amount of data that might be potentially lost as a result of a system failure? Recovery Time Objective (RTO) Press enter after select an option to check the answer Recovery Point Objective (RPO) Press enter after select an option to check the answer Disaster Recovery Plan (DRP) Press enter after select an option to check the answer Business Continuity Plan (BCP)

User Pablompg
by
4.8k points

1 Answer

6 votes

Answer:

Recovery point objective (RPO)

Step-by-step explanation:

RPO is described as the age of files that is necessary and compulsory to be recovered from backup storage for the normal operations of a company to resume in cases that a computer, system, or network goes down due to hardware, program, or communications failure.

It describes a period of time that an firm’s operations must be restored after a disruptive event, like a cyber attack, natural disaster or communications failure.

The RPO is often conveyed backward in time into the past from the event in which the failure occurs, and it can be specified within seconds, minutes, hours, or days. It an essential and crucial consideration in disaster recovery planning (DRP).

The RPO measures the time between the last data backup and the occurrence of a problem.

User Hriday Modi
by
5.5k points