Answer:
3
Step-by-step explanation:
Data provided in the question
Daily production = 105 units
Supplier lead time = 12 days
Safety stock = 1.75 days
Kanban size = 37 units
So by considering the above information, the required kanbans is
But before we have to determine the reorder point which is shown below:
= Daily production × (Lead time + safety stock)
= 105 units × (12 days + 1.75)
= 118.75 units
Now the required kanbans is
= Reorder point ÷ kanban size
= 118.75 units ÷ 37 units
= 3