Answer:
Annual demand (D) is 9700 units.
Number of Working days = 300 days per year
Lead time = 5 working days.
Calculate the Re-Order Point (ROP) using the following formula:
ROP = (Demand per day) x (lead time for a new order in days)
ROP = d x L
Where,
d = D / Number of working days
Substitute the values in equation (1)
ROP = (D / Number of working days) x Lead time
ROP = (9700 / 300) x 5
ROP = 161.67
ROP = 162 units