Given:
Service level = 95%
z = 1.65
Standard deviation = 8
Lead time demanded = 70
To find:
a. Safety stock level for BX-5
b. Appropriate reorder point
Solution:
The formula to calculate the safety stock is as follows,

On plugging-in the values we get,

a. Therefore, the safety stock for BX-5 is 10.24
The formula to calculate the reorder point is as follows,

On substituting the values we get,

b. The appropriate reorder point is 80.24