Zenich Corp manufactures laptops. The waiting time is 72 minutes before the start of production and the manufacturing lead time is 160 minutes per laptop. What is its manufacturing cycle​ efficiency? (Round to the nearest whole​ percent.)

User StefanK
by
6.8k points

1 Answer

3 votes

Answer:

The Manufacturing cycle​ efficiency = 69 %

Explanation:

The waiting time is = 72 minute

The manufacturing lead time is (
T_(lead) )= 160 minutes

Total cycle time (
T_(c) ) = 160 + 72 = 232 minutes

Manufacturing cycle​ efficiency =
(T_(lead) )/(T_(c) )

⇒ Manufacturing cycle​ efficiency =
(160)/(232)

⇒ Manufacturing cycle​ efficiency = 69 %

Therefore, the Manufacturing cycle​ efficiency = 69 %