13.0k views
3 votes
An end item​ "A" is assembled from two​ "B" components and two​ "C" subassemblies. The​ "C" subassembly is composed of one of each component​ "B" and​ "D." If the gross requirement for​ "A" is 100​ units, what is the demand for component​ "B"?

User JGS
by
7.7k points

1 Answer

1 vote

Answer:

400 units

Step-by-step explanation:

User JMSH
by
8.2k points
Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.

9.4m questions

12.2m answers

Categories