A contractor hires 150 men to pave Philip Goldson highway in 30 days. How many men will he hire to do the same work in 20 days?
asked
Jul 23, 2023
109k
views
19
votes
a contractor hires 150 men to pave Philip Goldson highway in 30 days. How many men will he hire to do the same work in 20 days?
Mathematics
high-school
Rohit Garg
asked
by
Rohit Garg
8.8k
points
answer
comment
share this
share
0 Comments
Please
log in
or
register
to add a comment.
Please
log in
or
register
to answer this question.
1
Answer
8
votes
Answer:
225 men
This conversion leads to the answer:
30 days → 150 men
1 days → (150 *30) men
1 days → 4500 men
20 days → (4500/20) men
20 days → 225 men
Xll
answered
Jul 27, 2023
by
Xll
7.7k
points
ask related question
comment
share this
0 Comments
Please
log in
or
register
to add a comment.
← Prev Question
Next Question →
Related questions
asked
Feb 22, 2023
64.0k
views
A contractor hired 150 workers to pave 30 miles of highway how many workers will they need to hire to pave 20 miles of highway in the same amount of time?
Vishwarajanand
asked
Feb 22, 2023
by
Vishwarajanand
8.2k
points
Mathematics
college
1
answer
2
votes
64.0k
views
asked
Jun 7, 2024
136k
views
a contractor hired 150 men to pave a road in 30 days. how many men will he hire to do the same work in 20 days
Lucrezia
asked
Jun 7, 2024
by
Lucrezia
7.9k
points
Mathematics
high-school
1
answer
2
votes
136k
views
asked
Feb 17, 2022
85.8k
views
a contractor hired 150 men to pave a road in 30 days how many men would he hire to do the same work in 10 days
Mochidino
asked
Feb 17, 2022
by
Mochidino
7.8k
points
Mathematics
college
1
answer
22
votes
85.8k
views
Ask a Question
Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.
9.4m
questions
12.2m
answers
Other Questions
How do you can you solve this problem 37 + y = 87; y =
What is .725 as a fraction
How do you estimate of 4 5/8 X 1/3
A bathtub is being filled with water. After 3 minutes 4/5 of the tub is full. Assuming the rate is constant, how much longer will it take to fill the tub?
Write words to match the expression. 24- ( 6+3)
Twitter
WhatsApp
Facebook
Reddit
LinkedIn
Email
Link Copied!
Copy
Search Qammunity.org