a contractor hires 150 men to pave Philip Goldson highway in 30 days. How many men will he hire to do the same work in 20 days?
asked
Jul 23, 2023
109k
views
19
votes
a contractor hires 150 men to pave Philip Goldson highway in 30 days. How many men will he hire to do the same work in 20 days?
Mathematics
high-school
Rohit Garg
asked
by
Rohit Garg
5.7k
points
answer
comment
share this
share
0 Comments
Please
log in
or
register
to add a comment.
Please
log in
or
register
to answer this question.
1
Answer
8
votes
Answer:
225 men
This conversion leads to the answer:
30 days → 150 men
1 days → (150 *30) men
1 days → 4500 men
20 days → (4500/20) men
20 days → 225 men
Xll
answered
Jul 27, 2023
by
Xll
5.1k
points
ask related question
comment
share this
0 Comments
Please
log in
or
register
to add a comment.
Ask a Question
Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.
5.7m
questions
7.5m
answers
Other Questions
Aliyah has $24 to spend on seven pencils. After buying them she had $10. How much did each pencil cost?
Evaluate a + b when a = –16.2 and b = –11.4 A. –27.6 B. –4.8 C. 4.8 D. 27.6
What is the value of x? (-4) - x = 5
Can someone help me with 5??? ASAP?
Solve for h 3h=7(2/7-3/7h)-10
Twitter
WhatsApp
Facebook
Reddit
LinkedIn
Email
Link Copied!
Copy
Search QAmmunity.org