Answer:
correct option is d.$7,511.61 unfavorable
Step-by-step explanation:
given data
standard material cost = $1.97 per yard
Actual material cost = $2.05 per yard
Standard yards = 4.67 per unit
Actual yards = 5.08 per unit
Units of production = 9300
solution
we get here Direct material quantity variance that is express as
Direct material quantity variance = (Standard quantity - actual quantity) × Standard rate .....................1
put here value and we will get
Direct material quantity variance = (9300 × 4.67 - 9300 × 5.08) × 1.97
Direct material quantity variance = −7511.61
so correct option is d.$7,511.61 unfavorable