Answer:
Time it will take to bring water to full capacity = 300 minutes
Longer it will take if pump is 500 gallons per minute rate = 900 minutes longer
Explanation:
Total Capacity = 1,000,000 gallons (1 mill)
It is full 2/5th, so it is empty:
1 - 2/5th = 3/5th
Now,
3/5th of 1,000,000 = 600,000
So, we need to fill up 600,000 gallons
The pump rate is 2000 gallons per minute, so the time it will take:
600,000/2000 = 300 minutes
If the pump was 500 gallons per minute rate, that would take:
600,000/500 = 1200 minutes
So, it will take:
1200 - 300 = 900 minutes longer