Answer:
Estimated manufacturing overhead rate= $40 per direct labor hour
Step-by-step explanation:
Giving the following information:
This period's estimated overhead cost is $100,000 and an estimated direct labor cost of $50,000 and 2,500 direct labor hours.
To calculate the estimated manufacturing overhead rate we need to use the following formula:
Estimated manufacturing overhead rate= total estimated overhead costs for the period/ total amount of allocation base
Estimated manufacturing overhead rate= 100,000/2,500= $40 per direct labor hour