Answer:
If the given situation turns into a legal dispute: Option D: the Court is likely to find that this is a unilateral mistake. However, since Builders knew (or should have known) that there was a mistake, the supplier will not be held to the $3,000 quote.
Step-by-step explanation:
Builders requested a bid from the supplier and while answering the bid, supplier made an error.
Unilateral mistake is the one in which only one party commits a mistake. The party that doesn't make the mistake gets to know about the mistake done by the other party. The contract is then made voidable by the mistaken party.
A voidable contract is like a formal agreement which is made between the two parties in which contract is decided to be made not enforced in case of any legal reason. It may include, if any of the party is not able to disclose a fact or a mistake, misrepresentation or any undue influence by someone on any of the parties. Thus, in the given case, court will ,likely find this as unilateral fault.