Answer:
C. 1.25
Step-by-step explanation:
Mathematically;
Capacity utilization rate= actual output per hour / operating level rate per hour
Actually output per hour= 500units
Operating level rate per hour= 400
Hence,
Capacity utilization rate= 500/400
Capacity utilization rate= 1.25