Answer:
2.73 days, working together without interference
Explanation:
The following formulas are pertinent here: 1 job = (rate)(time) and
1 job
time = ---------------------
1 job / days
In this specific case, there are two rates: 1 job / 5 days and 1 job / 6 days.
The combined rate would be:
1 job 1 job 6 + 5
---------- + ------------ = --------------- = 11/30 job/day
5 days 6 days (6)(5)
and so we have:
1 job
time = ------------------------ = 30/11 days, or 2.73 days
(11/30)(job/day)