Answer:
1) THROUGHPUT TIME =9 DAYS
2) MCE = 0.3 OR 30%
3) THE PERCENTAGE IS 70%
4) DELIVERY CYCLE TIME = 23 DAYS
5) NEW MCE = 0.675 OR 67.5%
Step-by-step explanation:
1)-
THROUGHPUT TIME = PROCESS TIME + INSPECTION TIME + MOVE TIME + QUEUE TIME
= 2.7 + 0.3 + 1 + 5
= 9 DAYS
2)-
MCE = VALUE ADDED TIME / THROUGHPUT TIME
= 2.7 / 9
= 0.3 OR 30%
3)-
THE PERCENTAGE IS 70% BECAUSE THE MCE IS 30%, THEN 30% OF THE THROUGHPUT TIME WAS SPENT IN VALUE-ADDED ACTIVITIES.
4)-
DELIVERY CYCLE TIME = WAIT TIME + THROUGHPUT TIME
= 14.0 + 9.0
= 23 DAYS
5)-
NEW THROUGHPUT TIME = PROCESS TIME + INSPECTION TIME + MOVE TIME
= 2.7 + 0.3 + 1
= 4 DAYS
NEW MCE = VALUE ADDED TIME / NEW THROUGHPUT TIME
= 2.7 / 4
= 0.675 OR 67.5%