A company has budgeted fixed overhead of $1.00 per hour at expected capacity of 5,000 units which has a standard quantity of 2 hours per unit. The company actually produces 5,200 units and incurred total overhead costs of $12,000. The controllable variance is:__________

User GigiSan
by
2.7k points

1 Answer

3 votes

Answer:

$1,600 Unfavorable

Step-by-step explanation:

Given that,

Budgeted fixed overhead = $1.00 per hour

Expected capacity = 5,000 units

Standard quantity = 2 hours per unit

Actual units produced = 5,200

Total overhead costs = $12,000

Controllable variance:

= Actual Overhead cost - Budgeted cost of actual production

= $12,000 - (Actual units produced × Budgeted fixed overhead × Standard quantity)

= $12,000 - (5,200 × $1 × 2)

= $12,000 - $10,400

= $1,600 Unfavorable