Answer:
Allocated MOH= $342,000
Step-by-step explanation:
Giving the following information:
Sawyer Company used a predetermined overhead rate using estimated overhead of $382,500 and 8,500 estimated direct labor hours.
Actual direct labor hours= 7,600
To calculate the estimated manufacturing overhead rate we need to use the following formula:
Estimated manufacturing overhead rate= total estimated overhead costs for the period/ total amount of allocation base
Estimated manufacturing overhead rate= 382,500/8,500= $45 per direct labor hour
Now, we can allocate overhead:
Allocated MOH= Estimated manufacturing overhead rate* Actual amount of allocation base
Allocated MOH= 45*7,600= $342,000