Answer:
What is the total cost for the tennis ball department if labor-hours are used as the sole cost driver? (Round all intermediate calculations to three decimal places.)
The answer is $542,857
Step-by-step explanation:
HR costs = 100,000
Maintenance costs = $150,000
HR Cost=(100,000 x4/7)= $57,143
Maintenance Cost=(150,000 x4/7)=$85,714
Original Department Cost= $ 400,000
Therefore, Total Cost= $ 542,857 (answer)
Key notes:
40,000 labor hours for tennis balls
30,000 labor hours for racquet balls
Total labor hours = 70,000
Fraction to use = 40,000/70,000 = 4/7