Answer:
Step-by-step explanation:
Using the EOQ Formula = EOQ
D = Demand = 773
O = Ordering Cost =28
H = holding Cost = 11*33% =3.63
So we have :
EOQ=
EOQ=
EOQ=
EOQ=
EOQ= 109.20196
Previous per unit order cost = 28/773 =0.03622
No of Orders = D/o
No of Orders = 773/109.20196 =7.0786
Cost per order =109.20196*0.03622 =3.9555
Total order cost= 7.0786*3.9555=27.9998
At EOQ holding Cost is equal to Order Cost
New Order cost =27.9998
Holding Cost = 27.9998
New cost As per EOQ = 56
Previous (33+28) = 61
Net Saving = 5