Answer:
The cost per equivalent unit for materials for the month in the first processing department is closest to b) $17.42
Step-by-step explanation:
First Step
First Calculate the Units of Closing Work In progress.
We Know that the units coming IN the progress should equal units coming OUT of the process
Therefore Units of Closing Work In Progress is = 7000+1000-6500 = 1500
Second Step
Then Secondly Calculate the Total Cost of Raw Materials in the process based on WEIGHTED AVERAGE METHOD.
Therefore Cost of Raw Materials = 6300+126100=132400
Third Step
Calculate Total Equivalent Production Units of Both Completed and Transferred and Closing Work In Progress Units
Therefore Total Equivalent Production Units = 6500×100%+1500×50%=7250
Finally
Calculate Cost per equivalent unit for materials
Cost per equivalent unit=Total Cost of Raw Materials $ 132,400/Total Equivalent Production Units 7,250 = $18.26
Therefore The cost of $18.26 is closest to b) $17.42